Supply chain8 min read

Biocarbon for Steel: Thorold Moves to Ramp-Up

Thorold has moved from construction towards commercial biocarbon ramp-up. Steel buyers should now test the feedstock, specification, delivered volumes and carbon evidence before treating design capacity or projected savings as realised results.

On this page
  1. A milestone, not yet a performance result
  2. How the project’s capital stack reduces risk
  3. What the off-take route proves — and what it does not
  4. Six checks for steel buyers
  5. Build contracts around evidence, not enthusiasm
  6. The procurement lesson from Thorold

Key takeaways

  • Thorold has reached substantial construction completion, but final approvals, commissioning and sustained commercial performance remain ahead.
  • Public funding, project equity, strategic investment and an off-take route address different scale-up risks and should be assessed separately.
  • Steel buyers should verify feedstock traceability, product performance, qualified output and delivery rather than rely on design capacity.
  • Carbon claims need disclosed system boundaries, allocation rules, primary data, assurance and clear ownership of environmental attributes.

Thorold’s biocarbon project has reached a useful but easily overstated milestone. On 1 October 2026, CHAR Technologies said Phase 1 mechanical and electrical construction was substantially complete and that the facility would move into operational kick-off and commercial ramp-up. The company expects production and revenue to increase through the end of 2026, subject to final approvals as systems come online.1

For steel buyers, the announcement is not proof that nameplate output, product performance or carbon savings have been achieved. It is evidence that a first-of-a-kind supply project has moved from construction towards commissioning. That distinction matters when procurement teams evaluate emerging low-carbon materials.

A milestone, not yet a performance result

Phase 1 is designed to produce up to 5,500 tonnes of biocarbon a year. The facility is jointly owned by CHAR Technologies and the BMI Group, and ArcelorMittal Dofasco is identified as an intended customer under an earlier off-take agreement.1

Three different states must remain separate in a sourcing decision:

  • Construction completion: equipment and electrical work are substantially in place.
  • Commissioning: systems are tested, brought to temperature and approved for operation.
  • Commercial performance: product is delivered consistently at the required quality, volume and cost.

The October update places Thorold between the first and second states. It says final approvals from Ontario’s Electrical Safety Authority and Technical Standards and Safety Authority remain part of the immediate next steps.1 A buyer should therefore treat the 5,500-tonne figure as design capacity, not current output, and should not convert anticipated substitution into realised emissions reductions.

That cautious reading does not diminish the milestone. Commercialising an industrial material requires equipment, permits, customers and working capital to converge. It simply prevents a project update from becoming an unsupported product claim.

How the project’s capital stack reduces risk

Thorold illustrates how low-carbon material projects can combine public funding, strategic equity and customer demand.

The company says Canadian and Ontario programmes have provided several tranches of support, including Ontario funding approved in 2022 and 2025. Ontario’s December 2025 announcement described C$2.25 million from its Forest Biomass Program to help commercialise forest biocoal, alongside an earlier C$6.4 million provincial investment in the Thorold facility.2

At project level, BMI committed C$8 million and the partners established 50/50 ownership. The funding agreement was designed to cover the equity required for Phase 1, while a later phase involving renewable natural gas was expected to pursue debt financing.3

ArcelorMittal also invested C$6.6 million at corporate level in 2023 through its XCarb Innovation Fund. CHAR announced at the same time that ArcelorMittal Dofasco would purchase Thorold biocarbon for larger-scale trials, following earlier blast-furnace testing.4

Each instrument addresses a different risk. Grants can help bridge first-of-a-kind capital costs. Project equity absorbs development and ramp-up risk. Strategic investment can support scale-up and technical collaboration. An off-take route provides a demand signal and a pathway to industrial validation.

None removes execution risk on its own. Procurement teams should examine whether funding is committed or conditional, whether the project has enough liquidity for commissioning, and whether the off-take agreement obliges the customer to buy at specified quality and volume or primarily enables trials.

What the off-take route proves — and what it does not

An off-take agreement is valuable because it connects a new material with an operating customer. It can help a producer finance equipment, refine specifications and plan volumes. It may also show that the customer has completed enough technical review to proceed beyond a laboratory sample.

However, the agreement does not automatically establish that every tonne is a drop-in substitute, that the plant will reach design output, or that the buyer can claim a fixed emissions reduction. The 2023 announcement described larger-scale electric-arc-furnace trials and stated an aim of reducing greenhouse-gas emissions over four years.4 That is a prospective objective, not a verified outcome.

Independent technical literature supports the broader potential while reinforcing the need for process-specific validation. An EU-funded study found that biomass-derived char could substitute for coal in electric-arc-furnace trials, but also identified practical considerations including charging, injection, slag foaming and recovery of energy from volatile matter.5

Buyers should therefore ask for test results tied to their actual steelmaking route, product specification and operating conditions. Evidence from one furnace, facility or form of biocarbon should not be generalised without a documented technical basis.

Six checks for steel buyers

1. Trace the feedstock

Request the biomass type, source region, supplier, transport distance and eligibility rules. “Wood waste” can cover materially different streams. Buyers need to know whether feedstock is a mill by-product, forestry residue, otherwise unmerchantable wood or material diverted from another use.

The assessment should address legality, land-use risk, forest-management controls, moisture content and competing uses. Ask how batches are traced to the conversion plant and which documents will be retained for assurance. A renewable origin alone does not demonstrate a low life-cycle footprint.

2. Lock the product specification

Define fixed carbon, ash, moisture, volatile matter, particle size, density and mechanical strength, together with sampling and rejection rules. The useful specification depends on whether biocarbon is charged, injected or used in another metallurgical function.

Include a controlled change process. A producer should not alter feedstock mix, pyrolysis conditions or pellet formulation without notifying the customer when those changes could affect furnace performance or carbon accounting.

3. Separate design capacity from delivered volume

Ask for a monthly commissioning plan, qualified capacity, yield, downtime assumptions and inventory policy. Track tonnes produced, tonnes meeting specification and tonnes accepted by the customer separately.

Commercial contracts should use stage gates: first approved batch, sustained quality across several runs, minimum monthly delivery and demonstrated recovery after downtime. Volume commitments can rise only after each gate is passed.

4. Define the carbon-accounting boundary

The carbon claim needs a stated functional unit and system boundary. It should cover feedstock collection, preparation, transport, pyrolysis, product finishing and delivery, as applicable. It should also explain how energy and emissions are allocated when the same process produces biocarbon and gas.

ISO 14404-4 provides guidance on boundaries, emission factors and upstream treatment for calculating steel-plant carbon-dioxide intensity across different production routes.6 For purchased materials, the GHG Protocol recommends supplier-specific cradle-to-gate product data where it is sufficiently reliable, along with disclosure of methods, data sources, assurance and the share of primary data.7

This is where buyers should distinguish three metrics: the biocarbon product footprint, the change in steelmaking emissions after substitution, and the purchaser’s Scope 3 factor for the resulting steel. They are connected, but they are not interchangeable.

5. Test the comparability of steel claims

Do not compare headline kilograms of carbon dioxide equivalent without checking the production route, scrap share, co-product allocation, background datasets and reporting boundary. ResponsibleSteel’s September 2026 analysis found that methodological choices can materially influence product-level results, even when underlying site data are independently verified.8

Procurement teams should request both the reported value and the calculation file or assurance statement needed to understand it. The PACT steel guidance similarly emphasises product-level reporting from a specific asset as the basis for a climate-differentiated steel market.9

6. Prevent double counting

Contracts should state who owns the environmental attribute associated with substitution. If the steelmaker uses a lower product footprint, the biocarbon supplier should not sell the same reduction separately without a compatible chain-of-custody approach. The buyer also needs to know whether any credits or certificates are issued, retired or transferred.

Require a reconciliation between physical delivery, production records and any environmental claim. Where estimates are used during ramp-up, label them as estimates and replace them with primary data once stable operations allow.

Build contracts around evidence, not enthusiasm

A practical off-take or sourcing agreement should contain:

  • a specification schedule and agreed test methods;
  • commissioning and qualification milestones;
  • volume bands rather than an immediate nameplate assumption;
  • pricing rules for off-specification or trial material;
  • feedstock traceability and change-notification obligations;
  • an agreed life-cycle and steel-emissions methodology;
  • access to assurance evidence and proportionate audit rights;
  • ownership rules for environmental attributes; and
  • remedies for missed quality, volume or evidence requirements.

Buyers can also link commercial support to verified milestones. A longer commitment, faster payment, co-funded testing or a temporary premium may be justified when it helps overcome a genuine scale-up barrier. The benefit should reduce as performance risk falls, and it should not survive if the producer cannot provide the agreed evidence.

For a broader approach to financing factory-level transitions, see MindTrust’s guide to funding supplier decarbonisation in Asia. For product data controls, use the supplier product-carbon-footprint checklist.

The procurement lesson from Thorold

Thorold shows why first commercial plants need more than a promising technology. They need a credible feedstock route, patient capital, an industrial partner and a buyer prepared to test and use the output. The October milestone suggests those elements are converging, but commissioning, approvals and sustained delivery still have to prove the commercial case.

The right procurement response is neither to dismiss an emerging material nor to accept its headline claims. It is to build a staged contract that rewards verified progress. Start with traceable feedstock and a testable specification. Qualify the material in the intended process. Measure delivered volumes. Then calculate product and steel emissions using disclosed boundaries and assured primary data.

That approach lets buyers support scale-up without booking reductions before they exist. If your team is assessing low-carbon materials or supplier off-take structures, talk to our team about the technical, commercial and carbon evidence required for a defensible decision.

Frequently asked questions

What is biocarbon in steelmaking?

Biocarbon is a biomass-derived carbon material that may replace part of the fossil carbon used in steelmaking. Its suitability depends on the production route, physical and chemical specification, operating conditions and validated substitution rate.

Is Thorold already producing 5,500 tonnes of biocarbon a year?

No. CHAR Technologies describes 5,500 tonnes per year as the designed Phase 1 capacity. Its 1 October 2026 update said mechanical and electrical construction was substantially complete, with final approvals and commercial ramp-up still ahead.

What should buyers verify before sourcing biocarbon?

Verify feedstock origin and traceability, product specification, process-specific trial results, qualified monthly output, delivery performance, cradle-to-gate emissions, allocation rules and ownership of environmental attributes.

Can a buyer claim the producer's projected emissions savings?

Not automatically. The buyer needs evidence from actual deliveries and the intended steelmaking route, calculated within a disclosed boundary. Prospective targets and design assumptions should remain separate from verified product and steel emissions.

  • biocarbon
  • low-carbon steel
  • steel procurement
  • Scope 3
  • industrial decarbonisation

Sources

  1. CHAR Technologies, CHAR Tech Completes Thorold Phase 1; Pioneering Project Now Set for Commercial Biocarbon Ramp-Up (1 October 2026)
  2. Government of Ontario, Ontario Investing $2.2 Million to Unlock New Markets for Forest Biocoal (accessed 6 October 2026)
  3. CHAR Technologies, CHAR Tech Announces $8 Million BMI Group Investment in Thorold Renewable Energy Facility (2025)
  4. CHAR Technologies, C$6.6M Strategic Investment by ArcelorMittal and Annual Biocarbon Purchase Agreement (5 July 2023)
  5. Publications Office of the European Union, Biochar for a sustainable EAF steel production — GREENEAF2 (2018)
  6. ISO, ISO 14404-4:2020 — Calculation of carbon dioxide emission intensity from iron and steel production
  7. GHG Protocol, Technical Guidance for Calculating Scope 3 Emissions — Category 1 Purchased Goods and Services
  8. ResponsibleSteel, From Data to Decisions: Comparable GHG Emissions Data for Steel Procurement (1 September 2026)
  9. WBCSD PACT, Steel GHG Emissions Reporting Guidance (Version 1.0, 21 June 2023)