ArcelorMittal Gent Pilot Captures Over 90% of Treated CO2
On 28 October 2026, ArcelorMittal, MHI, BHP and Mitsubishi Development completed a pilot capturing over 90% of CO2 from blast-furnace gas at Gent. Here is what the result shows, what it doesn't, and what steel buyers should check before citing it.
On this page
Key takeaways
- ArcelorMittal, MHI, BHP and Mitsubishi Development reported a Gent pilot capturing over 90% of CO2 from blast-furnace gas, completed 28 October 2026.
- The partners model a site-level CO2-intensity cut of up to 24% from full-scale deployment on this one gas stream — a projection, not a measured result.
- Phase 1 captured CO2 before combustion only; the remaining carbon monoxide is still burned on site and releases CO2 at that point.
- Phase 2 will test a harder, post-combustion gas stream at the hot strip mill, with no published timeline yet.
- Two of the four partners funding the trial are also steelmaking raw-material suppliers, which buyers should weigh when reading the capture-rate claims.
On 28 October 2026, ArcelorMittal, Mitsubishi Heavy Industries (MHI), BHP and Mitsubishi Development announced the completion of Phase 1 of a carbon capture trial at ArcelorMittal’s integrated steelworks in Gent, Belgium, reporting CO2 capture rates above 90% from blast-furnace gas over more than 4,500 hours of testing [1][2].
The trial used MHI’s Advanced KM CDR Process™ to strip CO2 from blast-furnace off-gas before it is burned on site for power and heat. ArcelorMittal and MHI say applying the technology at full scale to this one gas stream could cut the Gent site’s CO2 intensity by up to 24%, a figure modelled at hot-rolled product level on a cradle-to-gate basis — not a measured, full-scale result [1][2].
What was — and wasn’t — demonstrated
Phase 1 captured CO2 from a single pre-combustion stream only. The carbon monoxide fraction of the same blast-furnace gas is still burned on site, releasing CO2 at that point, so the 24% figure reflects partial decarbonisation of one process, not the whole site. Phase 2, still to come, will test a harder post-combustion stream — the hot strip mill reheating furnace — under a more variable flue-gas profile. Neither partner has published a date for Phase 2 results or for any full-scale investment decision [1][2].
Why procurement and ESG teams should care
Buyers tracking supplier decarbonisation commitments will see “>90% capture” cited as evidence of near-term abatement. That number describes pilot performance on one gas stream tested over several thousand hours, not a verified cut in delivered steel’s carbon footprint. BHP and Mitsubishi Development, which help fund the trial, are also steelmaking raw-material suppliers with a commercial interest in the technology succeeding — a reason to read the capture-rate headline alongside the modelled, not measured, site-level figure.
Steel is also one of the sectors inside the EU’s Carbon Border Adjustment Mechanism, where importers must report embedded emissions tied to the production route used. A verified, full-scale capture result would be relevant evidence for that reporting; a pilot-stage, single-stream result is not, and treating it as such risks overstating a supplier’s actual CBAM or Scope 3 position.
What to check before citing the figures
Before using this pilot in a supplier scorecard or a product carbon claim, buyers should confirm whether a quoted figure reflects Phase 1 capture alone, hypothetical full-site deployment, or the unproven near-zero pathway; ask whether any verification is independent of ArcelorMittal, MHI, BHP and Mitsubishi Development; check the stated boundary (cradle-to-gate, hot-rolled product) before comparing it with other suppliers’ claims; and track Phase 2 results before assuming the reheating-furnace stream behaves the same way as blast-furnace gas.
For buyers assessing decarbonisation pathways across steel and aluminium supply chains more broadly, see our guide to decarbonising metals and aluminium in Asia. Teams that want help reading supplier carbon-capture claims before citing them can talk to our team.
Frequently asked questions
Has ArcelorMittal demonstrated a 24% cut in emissions at its Gent site?
No. The 24% figure is a modelled estimate of what full-scale deployment of the pilot technology could achieve on one gas stream, calculated at hot-rolled product level. It has not been measured at full scale.
What exactly did the Gent pilot capture?
CO2 from blast-furnace off-gas before combustion, using Mitsubishi Heavy Industries' Advanced KM CDR Process, during more than 4,500 hours of testing completed by 28 October 2026.
Does this make ArcelorMittal's Gent steel near-zero carbon?
No. Near-zero intensity would require capture across multiple emission points at full scale, which has not been demonstrated. Phase 1 covered a single pre-combustion stream only.
When will Phase 2 results be available?
ArcelorMittal and MHI have not published a date for Phase 2, which will test CO2 capture from the hot strip mill reheating furnace under a more variable flue-gas profile.